True or False: The Designer Selection Law requires that all fees in a design contract be stated as a percentage of the construction cost.

Prepare for the MCPPO Design and Construction Test. Use flashcards and multiple-choice questions with explanations for each answer. Sharpen your skills for exam success today!

The statement is false. The Designer Selection Law does not mandate that all fees in a design contract be expressed strictly as a percentage of the construction cost. Instead, design fees can be negotiated in various ways, such as on a fixed fee basis, hourly rates, or through other arrangements that both the designer and client agree upon. This flexibility allows for a variety of project types and scopes, accommodating different needs and circumstances in design contracts.

Moreover, the Designer Selection Law aims to ensure a fair process in selecting designers and evaluating proposals based on qualifications and project needs rather than strictly on cost, which allows for a more comprehensive assessment of value beyond just financial considerations.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy