What is a common cause for contractors to seek change orders due to interference?

Prepare for the MCPPO Design and Construction Test. Use flashcards and multiple-choice questions with explanations for each answer. Sharpen your skills for exam success today!

Contractors often seek change orders due to owner interference with task execution because such interference can significantly affect the work flow and progress on a project. When the owner makes changes to the project requirements, requests alterations, or engages in activities that disrupt the contractor's planned work schedule, it creates a situation where the original terms of the contract can no longer be fulfilled.

This interference may lead to delays, the need for rework, or additional costs that were not accounted for in the original contract, necessitating a change order to adjust the contract terms and compensation accordingly. Understanding that owner interference can impact not just the timeline but also the overall project execution is key for effective project management and maintaining project efficiency.

Insufficient planning and poor project management certainly contribute to conflicts, but they do so primarily by creating a less organized framework within which the project operates. Equipment malfunction is generally related to operational issues rather than decision-making or interference from the owner's side.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy