What type of delay occurs due to circumstances caused by both parties?

Prepare for the MCPPO Design and Construction Test. Use flashcards and multiple-choice questions with explanations for each answer. Sharpen your skills for exam success today!

Concurrent delay occurs when two or more delays impact a project simultaneously, and these delays are attributable to different parties involved in the project. This type of delay creates challenges in determining accountability since both parties are experiencing interruptions that affect the project schedule.

In concurrent delays, one party might be experiencing a delay caused by external factors, while another party might have its own delay due to different circumstances. This makes it difficult to assess responsibility and determine the impact on project timelines. Often, concurrent delays result in disputes over liability and the extent to which either party is entitled to extensions of time or compensation.

Understanding concurrent delay is important in the design and construction industry because it highlights the complexities involved when analyzing project schedules and determining possible remedies for delays. This knowledge assists professionals in effectively managing projects and addressing potential conflicts that arise during construction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy