Which section allows the owner to delay or suspend work for convenience?

Prepare for the MCPPO Design and Construction Test. Use flashcards and multiple-choice questions with explanations for each answer. Sharpen your skills for exam success today!

The correct choice is Section 39O, as this section specifically addresses the owner's right to delay or suspend work for convenience. This provision grants the owner the flexibility to halt construction activities without having to provide a reason, as long as it is communicated through a formal process outlined in the contract. This can be important for the owner to manage unforeseen circumstances or operational adjustments.

By allowing for work to be suspended without cause, Section 39O serves to protect the interests of the owner while also establishing clear protocols for compensation and schedule adjustment for the contractor. This section is designed to ensure that when an owner exercises this right, it is done in a fair manner, outlining the procedure for notifying the contractor and the implications for the timing and costs associated with the suspension.

Other sections do not address the owner's ability to suspend work for convenience, focusing instead on other contractual obligations or rights that may not provide this level of flexibility. Understanding this allows stakeholders to navigate contract terms regarding the management of construction projects effectively.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy